On the 27th September the first of the progress meetings took place with the builders.

Webcam Link:  Click Here

Build Week: 4

Anticipated Completion Date: 25th July 2019

Planned Progress: 8.5%

Actual Progress: 8.5%

Progress in Period:

Secured the site and erected perimeter heras fencing

Commenced site hoarding and gates

Installed site cabins

Complete cut and substantially completed fill

Commenced stoning car park and drop off areas to formation level

Commenced excavation and concreting of foundations

Next Progress Meeting: 25th October 2018

 