On the 25th October the first of the progress meetings took place with the builders.

Webcam Link:  Click Here

Build Week: 8

Anticipated Completion Date: 25th July 2019

Planned Progress: 17.02%

Actual Progress: 19.14%

Progress in Period:

Site Set-up completed
Completed tarmac base course to car park and entrance area
Completed foundations
Commenced ground floor slab preparation and waterproofing
Completed external drainage

Key Activities in Next Period:

Poor ground floor slab
Continue external drainage and ducting
Commence steel frame
Commence sports pitch works

Next Progress Meeting: 29th November 2018