On the 29th November a progress meeting took place with the builders.
Build Week: 13
Anticipated Completion Date: 25th July 2019
Planned Progress: 27.46%
Actual Progress: 27.89%
Progress in Period:
Completed ground floor slab
Continued drainage throughout the site
Commenced works to the car park area kerbs and block paving
Commenced steel frame
Key Activities in Next Period:
Complete steel frame
Continue external drainage and ducting
Erect scaffold hand rails and safety netting
Commence roof liner sheets
Commence SFS & CP board
Next Progress Meeting: 9th January 2019
Hunts Grove Build Progress Meeting 3