On the 29th November the first of the progress meetings took place with the builders.

Webcam Link:  Click Here

Build Week: 13

Anticipated Completion Date: 25th July 2019

Planned Progress: 27.46%

Actual Progress: 27.89%

Progress in Period:

Completed ground floor slab
Continued drainage throughout the site
Commenced works to the car park area kerbs and block paving
Commenced steel frame

Key Activities in Next Period:

Complete steel frame
Continue external drainage and ducting
Erect scaffold hand rails and safety netting
Commence roof liner sheets
Commence SFS & CP board

Next Progress Meeting: 9th January 2019