On the 30th January a progress meeting took place with the builders.

Webcam Link:  Click Here

Build Week: 22

Anticipated Completion Date: 25th July 2019

Planned Progress: 46.8%

Actual Progress: 40.4%

Despite being behind (due to weather) the builders are confident to meet the planned handover date.

Progress in Period:

Completed steel frame
Commenced roof liner sheets
Commenced single ply roof covering
Commenced SFS and CP board
Commenced curtain walling and windows
Commenced block work to plant room

Key Activities in Next Period:

Strike perimeter hand rail to north wing
Complete metal decking
Complete Metsec installation
Complete single ply membrane to north wing
Commence M&E installation

Next Progress Meeting: 28th February 2019