A progress meeting took place on the 28th March 2019

Camera Link: Click to view

Build Week: 30

Anticipated Completion Date: 25th July 2019

Planned Progress: 64%

Actual Progress: 56%

The program still shows the builders lagging behind but they are still confident of finishing on time.

Progress in Period:

Completed flat roof covering to entirety of roof
Commenced above ground brickwork
Completed Metsec installation
Completed metal and board to 1 side
Commenced underfloor heating and screed
Commenced skimming to North wing
Installed PV panels to roof
Commenced plant room

Key Activities in Next Period:

Complete brickwork
Commence render
Complete window and door installation
Substantially complete back boarding to partitions
Commence misting system installation
Commence carpentry
Commence decorating

Next Progress Meeting: 25th April 2019