A progress meeting took place on the 30th May 2019

Camera Link: Click to view

Build Week: 39

Anticipated Completion Date: 25th July 2019

Planned Progress: 82%

Actual Progress: 76%

The program still shows the builders lagging behind but they are still confident of finishing on time.

Progress in Period:

Continued 2nd Fix M&E
Substantially completed internal door-set install
Commenced fixed furniture install
Commenced ceiling grids
Commenced soft flooring install
Substantially completed plastering works
Commenced final decorations
Completed ground works to drop off area
Substantially completed render
Commenced canopy install
Commenced external fencing

Key Activities in Next Period:

Commenced M&E second fix
Commenced M&E commissioning
Continue soft flooring
Continue final decorations
Continue external ground works
Complete external timber cladding and parapet capping’s
Continue fixed furniture install
Commence landscaping works

Next Progress Meeting: 27th June 2019