A progress meeting took place on the 6th March 2019

Camera Link: Click to view

Build Week: 27

Anticipated Completion Date: 25th July 2019

Planned Progress: 59%

Actual Progress: 52%

The program still shows the builders lagging behind but they are still confident of finishing on time.

Progress in Period:

Completed roof liner sheets and vapour control layer to all of the roof
Completed entirety of roof to the North Wing
Completed SFS Insulation with the exception of the entrance lobby
Completed below ground tanking
Commenced 1st fix M&E installation
Commenced back boarding to internal partitions
Completed window and door install to North Wing.

Key Activities in Next Period:

Complete metal and board one side to all partitions
Substantially complete first fix M&E
Complete singly ply membrane to South Wing with roof lights and seams to follow
Complete window and door installation
Commence underfloor heating and screed

Next Progress Meeting: 25th April 2019